Assessment & restoration of an old 19th-Centurybuilding to address structural hazards – Aubagne (13)

Client

Client :

Logirem

projet

Nature du projet :

rehabilitation and hazard mitigation

lieu

Lieu :

Aubagne - South of France

construction

Nature du système constructif :

agence bureau detude Axiolis

120 m2

•••

Area

2020

•••

Study phase

120 000 €

•••

Construction budget

2021

•••

Construction Phase

Structural Assessment, Renovation, and Hazard Mitigation of an Existent Structure

AXIOLIS was commissioned to conduct a complete project management mission in the context of difficulties impacting the hazardous building at 21 Rue Martinot in Aubagne. This mission began with an emergency stabilization phase for the building, as required by the danger order. Following that, AXIOLIS performed a full diagnostic to determine the extent of the difficulties.

The structure has a ground level and four more stories. Rafters and wooden beams parallel to the facades support the floors and roofs, which are carried by load-bearing walls into which they penetrate by about a third, or even half, of the wall thickness. Neither the front nor the back facades are load-bearing. The neighboring buildings are not technically independent; the load-bearing wall between them is solitary and supports both buildings’ floors.
The detected faults mostly involve the timber floors, which have sectionedoff beams and severely degraded supporting components. Aside from that, the neighboring wall was swollen.

Nos missions et métiers 
réalisés sur ce projet

All of the subfloors were reinforced during construction by strengthening the timber beams (Kerto) and adding metal features. The underside was reinforced without the requirement for altering existing supports or destroying the screeds. This method not only shortened the construction timetable but also lowered expenditures, especially for finishing work. The inspection office validated the new, low-cost process.
Axiolis completed a full project management mission and execution study to guide the project owner up to the point of decontaminating the facility. This rigorous oversight enabled the building to be returned to a safe state in a timely and cost-effective manner.

Building in a state of disrepair masonry restoration
Refurbishment of a building in a state of disrepair
Renovation of a dilapidated building